Nene Waterfront Regeneration Project Milestones




  • November 2006 – Foyer scheme completed; Berthing facilities at Yacht harbour extended
  • April 2007 – Boat hoist and wet dock completed
  • November 2007 – Nene Parade Pedestrianisation Phase I completed
  • August 2008 – Boathouse Business Centre completed
  • January 2009 – Slipway facility and new workshops completed
  • May 2009 – Remediation of vacant sites completed
  • July 2009 – March 2011 – Infrastructure works including link road construction, junction improvements, and Nene Parade Pedestrianisation Phase II
  • April 2011 onwards (Provisional) – Residential/commercial development of vacant sites